ERC approves Citicore Solar Pangasinan 2 project
ERC approves Citicore Solar Pangasinan 2 project

Solar Power Surge ERC Approves Citicore's Pangasinan 2 Project - A New Era in Renewable Energy
The Philippines is at the forefront of a solar power revolution, with Citicore Solar Pangasinan 2 Inc. leading the charge. The company has recently received approval from the Energy Regulatory Commission (ERC) to connect its 80.1-megawatt alternating current (MWac) Binalonan solar power project to the National Grid Corp. of the Philippines' 69 kilovolt (kV) San Manuel substation.
A Monumental Project
Citicore Solar Pangasinan 2 will construct transmission facilities and connect its massive solar power project to the national grid, a feat that requires an estimated investment of P286.2 million, including the cost of power transformers. This ambitious project is designed to meet the rising demand for electricity in the Philippines, secure 20-year government contracts (via Green Energy Auction-2), and align with Citicore Renewable Energy Corp.'s target of adding 1 gigawatt of solar capacity annually.
As of August 11, 2025, the construction of the project was ongoing, with 30 percent completion. This progress is a testament to the dedication and expertise of Citicore Solar Pangasinan 2 Inc. in bringing this ambitious project to life.
ERC Guidance
The ERC emphasized that while approval has been granted, all power generation companies and grid users with similar projects must first obtain an authorization before proceeding with construction. This ensures coordinated system planning and maintains the integrity and security of the electricity grid, preventing the unchecked increase of unauthorized facilities that may compromise the system's reliability.
A Bright Future
As we look to the future, it's clear that solar power is here to stay. The Philippines' commitment to renewable energy will undoubtedly lead to a cleaner, more sustainable environment for generations to come.
Conclusion
The approval of Citicore Solar Pangasinan 2 Inc.'s project marks a significant milestone in the Philippines' transition to renewable energy. As professionals in the field of sustainability and beyond, it's essential to stay informed about the latest developments in initiatives like this one. With its focus on meeting rising demand, securing government contracts, and aligning with Citicore Renewable Energy Corp.'s target, this project is a shining example of what can be achieved through commitment and innovation.
Key Takeaways
The ERC has approved Citicore Solar Pangasinan 2 Inc.'s application to connect its solar facilities to the national grid.
The project will add 80.1-megawatt alternating current (MWac) to the Philippines' energy mix.
The estimated cost of the facilities is P286.2 million, including the cost of power transformers.
The project aligns with Citicore Renewable Energy Corp.'s target of adding 1 gigawatt of solar capacity annually.
Stay tuned for more updates on this and other exciting developments in the world of renewable energy!